Semiconductors

How the TSMC Brazos County fab timeline runs through 2031

ManufacturingMag Editorial·November 27, 2026

This article may contain AI-assisted content. Verify details with primary sources before acting on them.

Share:
Share

Why It Matters

TSMC Arizona Corporation's JETI application J0055 asks College Station ISD for a school-tax limit on a proposed $22.6 billion campus. The approval clocks are short. The build and tool-install spend, as reported from the filing, runs from 2027 to 2032, and it only happens if TSMC decides to build.

TSMC Arizona Corporation has filed Texas JETI application J0055. It asks College Station ISD for a school property-tax limit on the proposed TSMC Brazos County fab, a project the company calls the "TSMC Texas Advanced Semiconductor Manufacturing Campus," in the southern end of the county. The Texas Comptroller's J0055 record shows the application posted on 11/23/2026 and the Comptroller's recommendation packet posted on 11/24/2026. The status reads "Application Phase."

The filing doesn't commit TSMC to anything. Tom's Hardware reported that "nothing in the filing commits TSMC to buy the land or to build on it." It is still the most detailed public schedule available for one of the largest proposed industrial projects in Texas. For contractors, equipment suppliers and workforce planners, the dates matter more than the $22.6 billion total. The first local vote could come on Dec. 10.

The primary record: J0055

The Comptroller's page lists J0055 with College Station ISD as the school district and TSMC Arizona Corporation as the applicant. Note the applicant entity: the Texas request is filed by the same subsidiary that runs TSMC's Phoenix operations. WTAW reported that the Comptroller's office signed off in "just one business day." KBTX described that step as a recommendation that the governor and CSISD consider the application. According to Tom's Hardware, the Comptroller "says it has not audited or verified the company's projections."

The headline figures come from Brazos County statements as reported by KXXV and KBTX: an estimated $22.6 billion investment, at least 2,099 direct jobs, a $133,000 average annual salary, and advanced logic chips at 2nm or more advanced for AI, high-performance computing and mobile. County officials say the project is a fab, not a data center.

The dated calendar, past to future

DateMilestoneSource
Nov. 23, 2026J0055 application posted; Brazos County announces the proposed projectComptroller; KBTX
Nov. 24, 2026Comptroller recommendation packet postedComptroller; WTAW
Dec. 7, 2026, 6:30 p.m.Brazos County town hall, College Station High School Auditorium, 4002 Victoria AvenueKBTX
Dec. 10, 2026, 5 p.m.CSISD public hearings, CSISD Boardroom, 1812 Welsh Ave.; the board could vote on the agreementWTAW; KBTX
Within 30 days of the recommendationGovernor's office and CSISD must each actComptroller process page; Tex. Gov't Code §403.611
After both favorable determinationsApplicant, district and governor execute the agreementComptroller process page
Not scheduledTSMC final investment decision and land purchaseKBTX; Tom's Hardware
Dec. 31, 2026Federal §48D credit excludes property whose construction begins after this date26 U.S.C. §48D(e)
2027Construction projected to start; $729.0M building spendTom's Hardware, from the filing
2028$2.59B building spend; 757 new hiresTom's Hardware, from the filing
2029$5.28B building spend; tool spend begins at $649.2M; 1,110 new hiresTom's Hardware, from the filing
2030Tool and equipment spend peaks at $9.05B; 232 new hiresTom's Hardware, from the filing
2031Commercial operations; $3.36B equipment spendTom's Hardware, from the filing
2032$963.9M equipment spend; full operations in the filing's economic modelTom's Hardware, from the filing

What each approval step requires, and how fast it moves

JETI is the program Texas uses to limit school district maintenance and operations (M&O) taxes for large projects. According to the Office of the Governor and the Comptroller's program page, it gives a 10-year, 50% limitation on appraised value for M&O purposes, and both the governor and the school district have to approve. WTAW and KXXV reported that interest and sinking fund (debt) taxes still apply at full value. CSISD's bond-backed levy is therefore unaffected.

The Comptroller's process page sets the clocks:

  • The Comptroller has 60 days to recommend or not recommend. Here it took one business day.

  • The governor's office has 30 days after it receives notice of the recommendation.

  • The district has 30 days from the recommendation and must give hearing notice no later than the 15th day before the hearing. Tex. Gov't Code §403.611(a) requires the board to act "not later than the 30th day after the date the district receives" the application from the Comptroller.

  • After both approve, the parties execute the agreement and construction can begin. The incentive period runs up to 10 consecutive years starting once construction is complete. A three-year "maintain a viable presence" period follows.

Brazos County's own tax abatement is a separate track. KBTX and KXXV reported that the Commissioners Court would consider it in its own public hearings.

For a sense of pace, look one county over. In the SpaceX Terafab case in Grimes County, KBTX reported that the Comptroller acted on June 15, 2026. Both school boards voted 5-2 on July 14, and the governor's 30-day window closed on July 15. Under that pattern, the J0055 approvals would be settled within about a month of the Nov. 24 recommendation. The decision that actually releases construction money is TSMC's.

Bid windows: building spend comes first, tools and facility systems peak in 2030

Tom's Hardware's reading of the filing splits the $22.6 billion into $8.60 billion for buildings and real property and $14.02 billion for tooling, machinery and equipment. The second figure is 62% of the total and includes power, HVAC, cleanroom, water and gas systems. That split, plus the year-by-year table, tells each trade roughly when its work would arrive.

Illustration seen from above of a few concrete, soil and rebar samples on the left and a larger group of stainless tubing, a valve and a filter panel corner on the right.

Site, civil and shell (2027-2029). Building spend ramps from $729.0 million in 2027 to $2.59 billion in 2028 and $5.28 billion in 2029. The small first year fits site preparation, earthwork, utilities extension and foundations. The 2029 peak fits structure and envelope. General contractors, civil firms, concrete and steel suppliers would see the earliest packages, and the 2027 number is small enough that early work may go to a limited set of firms.

Mechanical, electrical and facility systems (2029-2031). Because the equipment line includes HVAC, cleanroom, water and gas systems, the jump from $649.2 million in 2029 to $9.05 billion in 2030 is the year mechanical and electrical subcontractors, cleanroom builders, ultrapure water and specialty gas vendors, and tool-install crews would be busiest. Spend stays heavy at $3.36 billion in 2031, then falls to $963.9 million in 2032. On this schedule the building and tool curves overlap in 2029. That's typical for fabs, and it's where labor competition between trades on the same site would be sharpest.

Operations staffing (2028-2030). Projected hiring is 0 in 2027, 757 in 2028, 1,110 in 2029 and 232 in 2030, for 2,099 total. Most of the hiring happens two to three years before the 2031 commercial operations date, so training providers, staffing firms and housing developers would feel the demand well ahead of first wafers.

Tom's Hardware also reported that the filing describes the mask shop as "co-located within the fab and integral to the manufacturing process." Suppliers of mask-related equipment and services should read that as part of the same campus scope, not a separate later project.

The Brazos site: 3,232 acres, not yet bought

KBTX places the site on just over 3,200 acres in Brazos County Precinct 1, generally north of Koppe Bridge Road and west of I&GN Road. Most of it lies outside College Station city limits but inside College Station ISD. WTAW and KXXV reported that about 3,232 acres would be designated "TSMC Reinvestment Zone No. 1" within College Station's extraterritorial jurisdiction and CSISD boundaries.

Illustration seen from above of a strapped bundle of unused survey stakes, a roll of orange flagging tape and a closed notebook on a land parcel plan with one tract outlined.

The parcels are under contract, but KBTX reported that county records show they haven't been purchased and that TSMC's filing says its agreements are not yet binding. Power would come from Bryan Texas Utilities. Wellborn Special Utility District serves the area today. The developer plans to buy water from a third party, and county officials expect no impact on local water resources. "We are very excited about this potential transformational opportunity for our citizens," County Manager Trevor Lansdown told KBTX.

Workforce math: 2,099 projected, 35 required

Tom's Hardware reported that the agreement "would require only 35" jobs, "the legal minimum." The Comptroller's program page sets 35 jobs and $50 million in investment as the floor for counties with 100,000 to 249,999 residents. The gap between 35 and 2,099 is the most important number in the filing for anyone planning a training program or a payroll-dependent business around this project. Only 35 jobs are contractually tied to the tax benefit. The rest is a projection.

If the projection holds, 2,099 jobs at the county's reported $133,000 average works out to roughly $279 million in annual payroll. That's our arithmetic, not a figure from the filing. Front-loaded hiring in 2028 and 2029 means technician and maintenance pipelines would need graduates in those years, not in 2031. A regional college or trade program that starts building fab-technician capacity on the strength of this filing alone takes on the same risk as a contractor: no final investment decision exists.

The Arizona alternative and the "determinative" tax limit

Tom's Hardware reported that the tax benefit is worth about $354.1 million, roughly 1.6% of the investment, and that TSMC calls the limit "determinative." TSMC also says Arizona offers "established operational efficiencies and lower capital risk." KBTX reported that TSMC's existing Phoenix campus is the out-of-state alternative and that Sherman, in North Texas, is also competing. Calling a benefit worth 1.6% of capex decisive suggests the comparison between sites is close enough that a few hundred million dollars could tip it.

The scale comparison favors Brazos on land. CNBC's site tour, republished by NBC DFW in December 2024, put TSMC's first Arizona fab on 1,100 acres. That fab's cost rose from about $12 billion to about $20 billion, and it was making 4nm chips at about 20,000 wafers per month. The Texas reinvestment zone is nearly three times that acreage. The Arizona cost growth is a reminder for estimators that early fab budgets move.

Timing favors Arizona. Tom's Hardware notes N2 volume production began in Taiwan in the fourth quarter of 2025 and that the Texas fab "wouldn't make 2nm or more advanced chips until 2031, six years after 2nm volume production began in Taiwan." A Texas campus would come online at a node TSMC will have been running for years elsewhere.

The federal clock: §48D and a 2027 start

The advanced manufacturing investment credit in 26 U.S.C. §48D is 35% for property placed in service after Dec. 31, 2025. Subsection (e) reads: "The credit allowed under this section shall not apply to property the construction of which begins after December 31, 2026." The filing, per Tom's Hardware, projects construction starting in 2027.

On the statute text as published, a 2027 construction start falls outside the credit. Applied to a $14.02 billion equipment line, a 35% rate is a far larger number than the $354.1 million school-tax benefit, so the federal cutoff has to figure in TSMC's comparison between an existing Arizona footprint and a new Texas site. Suppliers should treat it as a structural input to the investment decision. Don't assume the credit applies to this project.

Risk register for suppliers

  • No binding commitment. The land is under contract, not purchased, and the filing commits TSMC neither to buy nor to build.

  • Site competition. Sherman and Phoenix are both alternatives, and TSMC's own filing argues Arizona carries lower capital risk.

  • Unaudited projections. The Comptroller says it hasn't audited or verified the company's projections, so the year-by-year spend and hiring figures are TSMC's estimates.

  • Thin contractual floor. Only 35 jobs are required against 2,099 projected. Tom's Hardware reported that TSMC would have to post a performance bond equal to 10% of the benefit, roughly $35 million on a $354.1 million benefit.

  • Utilities. Power from BTU and water bought from a third party are plans, not built infrastructure. Utility extension work would be among the first scopes and among the first to slip if plans change.

  • Federal credit timing. The §48D construction-start cutoff precedes the filing's projected start.

Milestones to watch before spending on bid prep

  • Dec. 7 town hall. Listen for county abatement terms and any detail on utility and road commitments.

  • Dec. 10 CSISD hearing and vote. A favorable vote clears one of the two required determinations.

  • Governor's determination. Due within 30 days of receiving the recommendation. In the Terafab case, the outcome wasn't immediately public when the window closed.

  • Commissioners Court abatement hearings. These run separately from JETI.

  • Land closing. County records showing the parcels purchased would be the first hard signal of commitment.

  • TSMC final investment decision. Until this happens, the 2027 construction start and every bid window above are projections.

  • Prequalification outreach in 2027. If early-stage site packages show up, the $729 million first-year building budget suggests a limited initial scope. Size bid-prep spending to that, not to the $22.6 billion headline.

Sources

Share

Frequently asked questions

Has TSMC committed to building a fab in Brazos County?

No. The land is under contract but county records show it hasn't been purchased, and Tom's Hardware reported that nothing in the filing commits TSMC to buy the land or build on it. Sherman and TSMC's Phoenix campus are both competing for the project.

When does College Station ISD vote on the TSMC tax limit?

CSISD will hold public hearings on Thursday, Dec. 10, 2026, at 5 p.m. in the CSISD Boardroom at 1812 Welsh Ave., and the board could vote on the agreement there. Brazos County will hold a town hall on Dec. 7 at 6:30 p.m. at College Station High School.

When would the TSMC Brazos County fab start production?

Tom's Hardware's reading of the filing puts the construction start in 2027 and commercial operations in 2031, with full operations in 2032 in the filing's economic model.

How much is the JETI tax benefit worth to TSMC?

Tom's Hardware reported about $354.1 million, roughly 1.6% of the $22.6 billion investment. JETI limits school M&O taxable value by 50% for 10 years, while debt-service taxes still apply at full value.

Does the federal 35% chip investment credit apply to this project?

Under the current text of 26 U.S.C. §48D, the credit doesn't apply to property whose construction begins after Dec. 31, 2026. The filing projects construction starting in 2027.