The three companies that make high-bandwidth memory have already committed most of their 2027 output, and the HBM4 capacity expansion each is now paying for mostly comes online in 2027 or later. On its October 29 earnings call, Samsung said its 2027 HBM supply "is already sold out." On October 28, SK hynix said long-term agreements with 14 customers cover more than half of its production capacity for 2027 and 2028. Micron said on its September 30 call that it had raised calendar-2027 HBM pricing "significantly."
If your plant buys DDR4 for industrial controllers or LPDDR4 for vehicle modules, the important point is that HBM and conventional DRAM are made on the same wafers. According to Reuters' reporting, relayed by TrendForce, Samsung executive vice president Kim Taewoo expects HBM to take nearly 30% of the DRAM industry's wafer capacity in 2027, up from about 20%. This article separates what each maker has confirmed from what Korean and trade press have reported, gives dates for when the new capacity arrives, and turns that into allocation guidance for 2027.
Confirmed by the companies vs reported by the press
The two columns below don't measure the same things. The company statements cover contracts, spending and fab milestones. The press reports give wafer-per-month figures, which come from industry sources and which none of the three companies has confirmed.
| Maker | Company-stated | Press-reported (outlet, date) |
|---|---|---|
| SK hynix | M15X to run at maximum capacity by year-end 2026 to raise HBM4 output. HBM4 expected to pass HBM3E in shipments and revenue in Q4 2026. LTAs with 14 customers cover more than 50% of 2027 and 2028 capacity. (Q3 release, Oct 28, 2026) | HBM4 equipment orders for Cheongju P&T6, with move-in and setup targeted for 1H 2027. More than 20,000 HBM wafers a month once fully running. (ETNews, Nov 15, 2026, citing equipment-partner and industry sources) |
| Samsung | 2027 HBM supply sold out (Q3 call via Korea Herald, Oct 29, 2026). 2026 capex of about KRW 84.4 trillion. 2027 AI-driven demand expected to "far exceed" industry supply. (Q3 release, Oct 29, 2026) | Average monthly HBM wafer input of roughly 180,000 in 2026, rising to about 250,000 in 2027 (Seoul Economic Daily, Sept 20, 2026). More than half of 4nm foundry capacity assigned to HBM4 base dies (Digitimes, Sept 8; Money Today, Sept 21). |
| Micron | Calendar-2027 HBM pricing raised significantly. First wafer output from Idaho in mid-calendar 2027. HBM facility in Singapore ramping in 2027 ("next year," per the September call). Most of the added FY27 construction capex goes to cleanrooms that come online in late 2028 and beyond. (FQ4 FY26 call, Sept 30, 2026) | HBM capacity rising to 100,000 wafers a month by the end of 2026, up from 40,000 to 50,000 last year. (Asia Business Daily, Sept 12, 2026, citing industry sources) |
SK hynix: M15X now, P&T6 reportedly next
SK hynix reported Q3 2026 revenue of KRW 104.6 trillion and operating profit of KRW 83.3 trillion. Its results release says the company "will ramp up M15X to maximum capacity by the end of the year to increase HBM4 production" and expects HBM4 to overtake HBM3E in both shipment volume and revenue in the fourth quarter. Both are company plans and forecasts, not results already reported.
The release also says customers have committed a large share of future output. SK hynix has signed long-term agreements with 14 major customers, including leading cloud service providers, and the volume signed so far "corresponds to more than 50% of total production capacity for 2027 and 2028." It expects demand to exceed supply through 2030 and says it will "adjust the scale and timing of its investment flexibly." That wording leaves the company room to slow down if conditions change.
The latest reported step is P&T6. ETNews reported on November 15, citing equipment partners and industry sources, that SK hynix is discussing purchase orders for HBM4 manufacturing equipment. According to the report, the company is aiming for equipment move-in and setup in the first half of 2027 and has asked for some tools to arrive in Q1. Cheongju P&T6 is the likely site, and once fully running it could add more than 20,000 HBM wafers a month. SK hynix didn't confirm the number. It said only that it "has continued placing equipment orders in line with its plans." Treat the 20,000-wafer figure as ETNews' sourcing, not company guidance.
Samsung: wafer input up about 40%, and a crowded 4nm foundry
Seoul Economic Daily, citing industry sources, puts Samsung's average monthly HBM wafer input at roughly 180,000 wafers in 2026 and about 250,000 in 2027, an increase of about 40%. The same report expects HBM4-family products to rise to about 80% of Samsung's HBM shipments from around 40%, with HBM4-family output "expected to more than double." Samsung began mass-production shipments of HBM4 in February 2026, using its 1c DRAM process and a 4nm base die. The wafer figures are industry estimates, not numbers Samsung has published.
Samsung did publish its spending and contract figures. The Q3 release reports company operating profit of KRW 107.4 trillion on revenue of KRW 195.3 trillion, with the DS (chip) division contributing KRW 106.5 trillion of that profit. Q3 capex was KRW 29 trillion, and full-year 2026 capex is expected at about KRW 84.4 trillion, of which KRW 76.8 trillion is in DS. On the call, as reported by The Korea Herald, Samsung said HBM4 was about 60% of its HBM revenue and that HBM4 revenue more than tripled in the quarter. It has signed long-term memory supply agreements with 10 major customers, is negotiating with 10 more, and aims to cover 60% to 70% of its production capacity with such agreements by 2030.
The 4nm base-die squeeze
HBM4 needs a logic base die, and Samsung makes its own on its foundry's 4nm process. Digitimes reported on September 8 that Samsung is giving more than half of its 4nm foundry capacity to HBM4 base dies. Money Today reported the same allocation on September 21, also citing industry sources, and added that the 4nm lines are "already operating at full capacity," that Samsung "recently raised prices for new 4nm orders," and that HBM4 base-die prices reportedly went up as well. According to Money Today, Samsung is considering adding 4nm capacity and building new 2nm lines for HBM5 base dies. It also reports that Groq's 3 LPU is made on Samsung 4nm.
Samsung's own Q3 release credits base-die sales growth for a "notable revenue and earnings improvement" in its foundry business. Its 2027 foundry outlook points to growth from 4nm and 2nm and to the start of operations at its new fab in Taylor, Texas. On the call, Samsung said that "capacity expansion at advanced nodes is not keeping pace with demand."
This affects buyers who never purchase HBM. A fabless company or industrial ASIC house with a design on Samsung 4nm now competes for wafer starts with Samsung's own memory business, on lines reported to be full, at prices reported to be rising for new orders. If a motor-drive controller, vision processor or gateway chip on your BOM comes from Samsung 4nm, ask that supplier about its 2027 wafer allocation now.
Wafer math for buyers outside AI
The industry-level figure matters most for plant operators. As reported by Reuters on September 29 and relayed by TrendForce, Kim Taewoo said HBM will account for nearly 30% of total DRAM industry wafer capacity in 2027, up from about 20%. He also noted that HBM and conventional DRAM compete for the same wafer capacity. Unless total wafer capacity grows at least as fast, a ten-point gain in HBM's share leaves fewer wafers for DDR4, DDR5 and LPDDR parts, and the largest new cleanrooms in this cycle aren't due until late 2028.

TrendForce's own forecasts point the same way. Its August 4 release says "DRAM supply will remain tight through 2027" and projects HBM bit shipments up 50% to 60% year over year in 2027. It also says NVIDIA has started widening its evaluation of the HBM configuration for Rubin Ultra, for which 12-Hi HBM4e had been the baseline. TrendForce's September 29 release projects the 2027 HBM blended average selling price to "jump 121% YoY," expects the market to stay supply-constrained in 2027, and describes HBM and conventional DRAM as "in competition for limited advanced-process and wafer capacity." It also expects 8-Hi HBM to carry a premium of roughly 10% to 20% per gigabit over 12-Hi products in 2027.
Market share helps explain why the reported Micron figure matters. Asia Business Daily cites Counterpoint Research Q2 HBM shares of 50% for SK hynix, 33% for Samsung and 18% for Micron. It also cites industry estimates that Samsung and SK hynix each run around 150,000 to 200,000 HBM wafers a month. Even at a reported 100,000 wafers a month, Micron would remain the smallest of the three.
Hyperscalers want to buy HBM directly
Pressure is also building on the customer side. Digitimes reported on November 19 that "Google is looking to buy high-bandwidth memory (HBM) directly for AI chips developed with MediaTek," which could change how the three memory makers negotiate with their largest customers. TrendForce, citing Chosun Biz on November 18, said Google is "reportedly moving toward" direct purchases instead of Broadcom's turnkey model. No decision has been confirmed, and none of the companies involved has commented.
Counterpoint Research has put a number on the motive. As reported by The Korea Herald on November 11, Counterpoint estimates that Broadcom's turnkey model "adds a 15 to 20 percent markup to HBM costs." Counterpoint's David Wu said Google is bringing chip design and HBM procurement in-house "starting with Zebrafish," the TPU 8t. SK hynix has proposed co-designing customized HBM for future TPUs, and Samsung and Broadcom signed an MOU in July covering HBM, foundry and packaging.
For industrial buyers, the effect runs through the contract book. When a hyperscaler buys HBM directly and signs its own long-term agreements, it takes a larger and more direct share of each maker's committed capacity. That leaves less room for smaller customers that buy through distribution or on short-term contracts.
What 2027 allocation looks like for industrial and automotive buyers
Micron gave the clearest statement on how it is allocating supply. According to the summary of its FQ4 FY26 call transcript, more than 75% of fiscal 2027 shipments are already under customer allocation or contract. Business executive Manish Bhatia said "customers are choosing to maximize the compute silicon shipments they can make with the available memory supply." He also said "it's important for us to be maintaining diversified supply to all our end markets." The same summary puts automotive and embedded revenue at $6.82 billion, up from $4.63 billion the prior quarter. Industrial and automotive customers are still being served, but mostly under contract, and the uncommitted share of supply is small.
Add the other two makers' commitments. SK hynix has contracted more than half of its 2027 and 2028 capacity, and Samsung wants long-term agreements covering 60% to 70% of its capacity by 2030. The supply left for spot buys and short-notice orders is shrinking at all three suppliers.
Automotive buyers face a longer timeline. Counterpoint Research's August 22 report, "Memory Crisis in the Automotive Industry," says "DDR4/LPDDR4 tightness for automotive customers will extend beyond 2027." It says automakers and suppliers are responding with "a mix of long-term supply agreements and a shift to next-generation memory types, such as DDR5." Counterpoint expects substitution led by CXMT could ease pressure over the long run, but only in China's market.
Why Micron's constraint is cleanroom space
Micron's numbers show how much money is going into the business: FY26 revenue of $133.19 billion against $37.38 billion in FY25, and net capex of $27.37 billion for the fiscal year, per its September 30 release. Spending isn't what limits supply. Building space is. Bhatia said "the majority of the construction CapEx increase for fiscal '27 versus our prior plans is for clean rooms" that "will come online in late '28 and beyond." He also pointed to trade ratios, with "future more complex HBM having higher trade ratios," meaning each new HBM generation uses more wafer capacity per bit shipped. On when the market balances, he said: "we really don't have line of sight to when supply and demand balances."

Tools can be ordered and installed within a year, as the reported P&T6 schedule shows. A new cleanroom takes much longer. Through 2027 and most of 2028, added HBM output has to come from fitting out existing space, and in practice much of that space would otherwise make conventional DRAM.
Capacity milestones by date
-
Q4 2026: SK hynix expects HBM4 to pass HBM3E in shipments and revenue, with M15X at maximum capacity by year-end (company).
-
End of 2026: Micron HBM capacity reported at 100,000 wafers a month (Asia Business Daily, unconfirmed).
-
Q1 to 1H 2027: Reported delivery and setup of SK hynix HBM4 tools, likely at P&T6 (ETNews, unconfirmed).
-
2027: Micron's Singapore HBM facility ramps. Samsung expects its Taylor, Texas fab to begin operations (company).
-
Mid-2027: First wafer output from Micron's Idaho facility (company).
-
Late 2028 and beyond: Micron's new cleanroom space comes online (company).
-
Through 2030: SK hynix expects demand to exceed supply (company forecast).
What to do before 2027 contracts close
-
Map BOM exposure to DDR4 and LPDDR4. List every assembly, controller and module that uses these parts, including memory on boards you buy from suppliers. Counterpoint's view that automotive tightness extends beyond 2027 suggests these parts won't get easier to source soon.
-
Time your long-term agreement talks to the suppliers' planning cycle. SK hynix has already contracted more than half of 2027 and 2028, and Micron more than 75% of FY27 shipments. If you want contracted volume for 2028, start negotiating while those allocations are still open.
-
Budget now for a DDR5 or LPDDR5 migration. Counterpoint says automotive suppliers are already moving this way. Requalification costs engineering hours, test time and in some cases customer approval, so it belongs in the 2027 capex and engineering plan.
-
Ask your ASIC and controller suppliers whether they depend on Samsung 4nm. If 4nm lines are full and new orders cost more, as reported, delays and price increases can reach you through parts that contain no HBM.
-
Track the dated milestones above. Whether P&T6 setup happens in 1H 2027, Idaho produces its first wafers in mid-2027 and Singapore ramps on schedule will show whether 2028 supply eases or stays tight.
Related reading
-
How to Compare Additive Manufacturing Quotes on the Same Footing
-
Can a Plant Stack Federal Apprentice Payments With State Grants?
-
How to Lock In 2027 Memory Supply in the Automotive Memory Chip Shortage
-
How the silicon interposer became the bottleneck in AI chip supply
Sources
-
SK hynix Announces Q3 2026 Business Results, SK hynix Newsroom, Oct 28, 2026
-
SK hynix HBM4 capacity expansion report, ETNews, Nov 15, 2026
-
Samsung Electronics Announces Third Quarter 2026 Results, Samsung Newsroom, Oct 29, 2026
-
Samsung roars back in AI chip race with record W107tr profit, The Korea Herald, Oct 29, 2026
-
Samsung to Double HBM4 Output Next Year, Sources Say, Seoul Economic Daily, Sept 20, 2026
-
Samsung Foundry Smiles Amid HBM Boom, Money Today, Sept 21, 2026
-
Samsung allocates more than half of 4nm foundry capacity to HBM4, Digitimes, Sept 8, 2026
-
Micron's Bet with the '100,000 HBM Wafers', Asia Business Daily, Sept 12, 2026
-
Micron Technology Reports Record Fiscal Fourth Quarter and Full Year 2026 Results, Sept 30, 2026
-
DRAM Supply to Remain Tight in 2027, TrendForce, Aug 4, 2026
-
HBM Supply Constraints Persist, 2027 Price Outlook Revised Upward, TrendForce, Sept 29, 2026
-
Samsung Sees HBM Taking Nearly 30% of Industry DRAM Capacity in 2027, TrendForce News (relaying Reuters), Sept 29, 2026
-
Google looks to bypass Broadcom with direct HBM purchases, Digitimes, Nov 19, 2026
-
Google Reportedly Eyes Direct HBM Purchases for TPUs, TrendForce News, Nov 18, 2026
-
Google's AI chip expansion opens new doors for Samsung, SK hynix, The Korea Herald, Nov 11, 2026
-
Memory Crisis in the Automotive Industry, Counterpoint Research, Aug 22, 2026