How to build GM supplier automation plans that score on sourcing bids

ManufacturingMag Editorial·November 20, 2026

This article may contain AI-assisted content. Verify details with primary sources before acting on them.

Share:
Share

Why It Matters

GM is reportedly scoring the automation plans suppliers submit with new bids. This guide shows how to map each cell to the five reported OAMI levels, run payback on BLS wage data and time capex under permanent 100% bonus depreciation.

GM supplier automation plans used to be survey paperwork. Now they're part of the quote package. In March 2026, GM started sending parts suppliers a self-audit survey under its Overall Automation Maturity Index (OAMI). On Nov. 17, 2026, Reuters reported that suppliers bidding on new contracts are being asked to submit plans for automating their own operations. Reuters cited two people familiar with GM's supply base, who said GM is "using a scorecard to rate suppliers' automation efforts and considering the scores in contract decisions." GM's statement to Reuters did not confirm the scorecard.

That puts the work on the estimating and operations teams at tier-1 and tier-2 shops. The plan has to score well enough to keep the shop in contention, and it can't commit capital that the quoted program volumes won't pay back. This guide starts by separating what GM has said on the record from what has been reported. It then lays out a cell-by-cell method and a payback worksheet you can fill in with your own quotes.

What has GM said on the record about supplier automation?

On the record, GM describes OAMI as a benchmarking survey, not a mandate. Patrick Sullivan, GM's Global Purchasing and Supply Chain Communications Lead, told AutoGuide that "GM has implemented a survey wherein suppliers benchmark their current levels of automation." He said that "there is currently no industry standard to measure automation across suppliers", that the survey "reflects a moment in time," and that "The associated metrics are goals (not requirements)." GM also says there is no single deadline.

The firmer-sounding details come from people speaking anonymously. A supplier writing a plan should treat the two groups of claims differently.

ClaimStatusSource
Suppliers benchmark their automation levels through a GM surveyOn the record (GM)Sullivan, via AutoGuide
The metrics are "goals (not requirements)"; not a mandate; no single deadlineOn the record (GM)Sullivan and GM, via AutoGuide
No industry standard exists to measure supplier automationOn the record (GM)Sullivan, via AutoGuide
GM is targeting 4.5 out of 5 on the scaleReported, anonymous sourcesCrain's Detroit Business, as relayed by AutoGuide
GM sometimes audits supplier plants directlyReportedAutoGuide
Bidders must submit automation plans, which GM rates on a scorecard and weighs in contract decisionsReported, two anonymous sourcesReuters, Nov. 17, 2026

According to AutoGuide, several supplier executives believe they're expected to reach those levels or risk losing future business. Whether or not the target is formal, the safe planning assumption is that the score will be read alongside price, quality and delivery.

Key dates in GM's automation push

  • March 2026: GM starts sending OAMI surveys. Suppliers audit their operations against GM criteria covering raw-material purchasing through production and final delivery (AutoGuide).

  • July 2026: The program becomes public in trade and auto press, along with the reported 4.5 target and supplier concerns about cost, funding and how savings would be split.

  • Nov. 17, 2026: Reuters reports the bid-stage automation plans and the scorecard. It also reports GM is "aiming to increase use of robots and other automation by 20% at its North American factories by 2028," citing two people familiar with the matter. Reuters didn't give a baseline for the 20%.

  • Spring 2028: The UAW contracts with GM, Ford and Stellantis expire (Reuters).

The 2028 dates line up, so expect the pressure to hold through at least the next contract cycle.

What are the five OAMI levels?

As reported by AutoGuide, the five levels from lowest to highest are manual operations, basic mechanization, semiautomation, integrated automation, and smart factory/adaptive automation. Suppliers rate themselves on this scale, and GM checks some plants with its own audits.

The scope matters more than the labels. The survey reportedly covers purchasing, production and delivery, so the score isn't only a robot count. How material moves, how data flows between machines and systems, and how parts are inspected all fall inside it. A shop with few robots but automated receiving, barcode or RFID traceability and inline gauging feeding its MES may have a better case than its robot count suggests.

We found no public GM document that sets out the detailed OAMI scoring rubric. All public detail comes from press reports and GM spokesperson statements. The mapping below is therefore an interpretation a supplier can defend with evidence. It is not GM's specification.

Step 1: How do you map your cells to the OAMI scale?

Start with an inventory covering every process step from the receiving dock to the shipping dock, including the parts nobody calls "production." For each step, record the level you'd claim and the evidence behind it. Write the evidence as something an auditor could see on a walk.

Object-focused illustration of a ruby-tipped gauging probe inside a machined aluminum bore held by a sensing fixture, lit by a single warm lamp on a dark background.

AreaWhat to recordEvidence that supports a higher level
Purchasing and receivingHow orders are released, how inbound material is identified and loggedEDI or portal releases, scanned receipts posting to inventory without rekeying
Material flowHow parts move between operationsConveyors, AMRs or tuggers on fixed routes, kanban signals generated by the system
Process cellsLoad, process, unload: which steps a person doesRobot or automated load/unload, fixtures with sensing, automatic changeover
InspectionWhere and how dimensions and defects are checkedInline vision or gauging with results stored by serial or lot
Data and controlWhether machines report status and counts on their ownMachine data feeding MES or a historian, OEE calculated from the machine rather than from clipboards
Pack and shipLabeling, packing, ASN generationAutomated labeling and ASNs generated from production records

Rate each line conservatively. If GM audits the plant, a self-score that doesn't hold up on the floor hurts your credibility on every other line. Date the file and call it a baseline. That's how GM describes the survey itself ("a moment in time"), and it lets you show movement at the next re-survey.

Step 2: Sort the plan into show, phase and defer

With the map done, put every automation opportunity in one of three buckets.

  • Show: automation that's already installed or already funded. It goes into the plan as current state, with photos, data exports or purchase orders.

  • Phase: projects that pay back at the volumes quoted on the program you're bidding. These get dates tied to award, PPAP or launch milestones.

  • Defer: projects that only pay back at higher volume or over a longer program life. Don't drop them. Name the trigger that would release them, such as an annual volume, a second program on the same line or an extension of the program's life.

A deferred project with a stated trigger still shows GM a path up the scale. It also keeps you from booking capex against volumes that may not show up.

How to calculate payback on a supplier automation project

Simple payback is installed cost divided by annual net savings. We didn't find verified prices for robots, cobots or integration, so the worksheet leaves those lines for your integrator's quotes. The wage side can use public data. In the BLS May 2023 occupational estimates for motor vehicle parts manufacturing (NAICS 336300), the mean wage for miscellaneous assemblers and fabricators, an occupation with 132,430 workers in the industry, is $19.48 an hour (median $18.67). Welders, cutters, solderers and brazers average $21.27. Industrial machinery mechanics average $29.85. The mean for all production occupations is $22.15.

LineInputBenchmark or example
AHourly wage of displaced or redeployed position$19.48 (assembler mean, BLS May 2023) or your payroll rate
BAnnual hours per shift position2,080
CPositions affected per shift x shiftsExample: 1 x 2 = 2
DGross wage savings (A x B x C)About $81,037 (about $40,518 per shift position)
EYour benefits and burden load on DYour rate
FAdded maintenance laborExample: 0.25 of a mechanic at $29.85 x 2,080 = about $15,522
GAdded running cost: power, spares, consumables, softwareYour quotes
HQuality and scrap gains, if measuredYour data
IAnnual net savings (D + E + H - F - G)Calculated
JInstalled cost: equipment, tooling, guarding, integration, commissioningYour quotes
KSimple payback in years (J / I)Calculated

In the example, wages alone net out to about $65,515 a year once the maintenance time is subtracted. That's before burden, running costs or quality effects. These figures are wages only, and the BLS numbers are a May 2023 benchmark, so use your own payroll rate where you have it.

Two adjustments often get left out. First, an automated cell running two shifts costs more per hour when it's down than a manual cell does, because there's no crew to fall back on. Our downtime cost calculator separates lost contribution from incremental recovery costs, and that's the right input for line G. Second, payback has to fit inside the program life you're quoting. A project that pays back in year five of a four-year award belongs in the defer bucket.

How does 100% bonus depreciation change the timing?

It shortens after-tax payback by moving the deduction into the first year. On Jan. 14, 2026, the IRS announced Notice 2026-11, interim guidance on the permanent 100% additional first-year depreciation deduction for eligible property acquired after Jan. 19, 2025, under the One, Big, Beautiful Bill. For property placed in service in the first tax year ending after Jan. 19, 2025, taxpayers can elect 40% instead of 100%, or 60% for certain long-production-period property.

Object-focused illustration of a robot base plate anchored to a concrete floor with paint-striped bolts and fresh grout, lit by a single warm lamp.

For the plan, put acquisition and in-service dates next to each phased project. Since the provision is permanent, there's no expiring cliff to race. What changes is which tax year gets the deduction, and that should match the year your cash flow can use it. Ask your tax adviser to run the after-tax version of line K before the quote goes out.

Are other GM suppliers already buying robots?

Yes. Supplier orders are growing much faster than automaker orders. According to A3 data reported by The Robot Report, North American robot orders in Q3 2026 totaled 10,989 units worth $723.5 million, up 24.8% in units and 26.1% in value from a year earlier. Automotive component suppliers increased orders 90.4% in the quarter, while automotive OEM orders rose 7.5%. For the first nine months of 2026, orders totaled 28,984 robots worth about $1.89 billion.

Installations had been flat. The IFR's preliminary figures show about 38,000 industrial robots installed in the U.S. in 2025, up 11%, with automotive installations at 13,500, down 1%. RoboticsTomorrow, reporting IFR's World Robotics 2026, gives a final U.S. figure of 38,400, up 12%, with the U.S. passing Japan (36,200) as the second-largest market after China. IFR President Jane Heffner said, "At the same time automotive has stayed stable as the largest customer."

For a supplier deciding on timing, that's a reason to get integrator quotes and lead times early. If component suppliers keep ordering at Q3's pace, phased projects dated for 2027 could compete for the same integration capacity.

Writing the plan without overcommitting

Every line in the plan should be either a firm commitment or a conditional one, and the document should say which. Firm commitments are funded projects with dates. Conditional ones are tied to a trigger the customer controls, such as award, volume or program life.

The supplier concerns reported in July carry over to the commercial terms. AutoGuide reported that suppliers were worried about the cost of major upgrades, how they'd be funded and how any savings would be split with GM. Put those questions in the quote instead of leaving them for later. State whether the automation capital is recovered in piece price, amortized over the award or depends on volume. If the program expects annual price-downs, say how automation savings figure into them. A plan that scores well but gives away the savings in year two leaves you with a worse margin on newer equipment.

What does the push mean for the supplier workforce?

GM's own labor costs are part of the reason. Reuters reported that GM estimated the 2023 UAW contract would add about $575 per vehicle in labor costs, while Ford estimated $900, and cited GM's "higher labor and onshoring costs." Reuters also reported that GM is building its own autonomous mobile robots at its Kokomo, Indiana, plant to move parts around its factories, while still buying robotics from outside suppliers. GM said last year it had about 100 roboticists, AI engineers and hardware specialists working on advanced robotics.

The union opposes it. "We don't need more robots so GM can do another stock buyback," UAW Vice President Ryan Hiestand said in a statement reported by Reuters. The UAW represents about 50,000 GM factory workers. Mikell Taylor, GM's director of robotics strategy, described the aim to Reuters as a combination: "How do I get the best out of both the people here and the machines here to get as much efficiency and quality as I can?"

At the plant level, moving up the scale changes who you need. Fewer people load parts, and more people maintain, program and handle exceptions. The BLS data shows that gap in pay: $29.85 an hour for industrial machinery mechanics against $19.48 for assemblers, with about 12,700 mechanics working in the industry. A plan that adds integrated cells without a matching maintenance and controls pipeline, whether that's apprenticeships, upskilling current operators or hiring, is promising uptime the shop can't support. Put the staffing plan in the document. It also answers the people-and-machines question GM's robotics lead raised.

Checklist before the next GM quote

  • A dated baseline evidence file: photos, data exports and POs for every automation claim.

  • A level-by-cell map covering receiving through shipping, with conservative ratings.

  • Phased capex with each project tied to an award, volume or program-life trigger.

  • A payback sheet with your wage rates, burden, maintenance labor, downtime cost and after-tax timing under Notice 2026-11.

  • Written commercial terms on who funds the automation and how savings are shared.

  • A maintenance and controls staffing plan that matches the automation level you're claiming.

  • A named owner for the annual re-survey, so next year's score shows progress against this baseline.

Sources

Share

Frequently asked questions

Does GM require suppliers to automate?

GM says no. Its purchasing communications lead called the OAMI metrics "goals (not requirements)" and said there is no single deadline. Reuters, citing two anonymous sources, reported that GM scores automation plans submitted with new bids and weighs the scores in contract decisions.

What is GM's Overall Automation Maturity Index (OAMI)?

OAMI is a survey GM began sending suppliers in March 2026. Suppliers use it to self-audit their operations from raw-material purchasing through delivery on five levels: manual operations, basic mechanization, semiautomation, integrated automation, and smart factory/adaptive automation. GM audits some plants directly.

What OAMI score is GM targeting?

People familiar with the matter told Crain's Detroit Business, as relayed by AutoGuide, that GM is targeting 4.5 out of 5. GM hasn't published a scoring rubric and describes the survey as a benchmark of a moment in time.

Are auto suppliers increasing robot purchases?

Yes. A3 data reported by The Robot Report shows North American orders from automotive component suppliers up 90.4% in Q3 2026, compared with a 7.5% rise in automotive OEM orders.

How does bonus depreciation affect automation payback?

IRS Notice 2026-11 covers the permanent 100% first-year depreciation deduction for eligible property acquired after Jan. 19, 2025. Deducting the full cost in the first year brings the tax benefit forward and shortens after-tax payback, so put acquisition dates next to each project in the plan.