How the 737 MAX Production Rate 47 Target Kept Slipping

ManufacturingMag Editorial·November 14, 2026

This article may contain AI-assisted content. Verify details with primary sources before acting on them.

Share:
Share

Why It Matters

Weeks after Boeing pushed rate 47 into 2027, its commercial unit said it would cut about 5% of staff. This is a dated record of every slip since the first time Boeing hit 47, and what each one meant for suppliers.

On Nov. 9, 2026, Boeing Commercial Airplanes (BCA) CEO Stephanie Pope told employees in an internal memo that the unit would cut about 5% of its workforce through attrition and involuntary layoffs, with notices going out in December at the earliest, Reuters reported. The memo came 13 days after CEO Kelly Ortberg told investors on the Oct. 27 earnings call that the 737 MAX production rate 47 milestone would not be stable until next year. The memo didn't move the target. It put a labor cost on a delay that had already been announced. "Adjusting our production schedules and reducing aircraft output puts us in an overstaffed position," Pope wrote, according to AVweb and IBTimes UK.

Boeing has been here before. It built 47 a month in the last cycle, lost that rate, and has been planning to get back to it since at least 2023. Against the December 2023 master schedule that Reuters described as setting the pace for suppliers, stable rate 47 is now about two and a half years late. Rate 52 has slipped by roughly the same amount. If you supply this program, or any program run on an OEM's master schedule, the record below is worth reading slip by slip.

The timeline at a glance

DatePlan or eventOutcome
June 2018Boeing moves from 47 to 52 a monthRamp waited until Spirit restored on-time fuselage deliveries
March 2019Producing 52, heading to 57MAX grounded; Boeing builds 42 a month into storage, halts in January 2020
Oct. 2023Formal target of 50 a month in 2025-2026; internal plan of at least 57 by July 2025Overtaken by events
Dec. 2023Master schedule: 42 in Feb. 2024, 47.2 in Aug. 2024, 52.5 in Feb. 2025, 57.7 in Oct. 2025None of these dates held
Jan. 24, 2024FAA freezes 737 MAX expansionOutput capped at 38
Oct. 17, 2025FAA allows 42 a monthBoeing sets steps of five, at least six months apart
Q2 2026Transition to 47 begins, "this summer" goalStalls on wing production
Oct. 27, 2026Stable 47 pushed into 2027; 52 targeted for second half of 20272026 deliveries to fall short of 500
Nov. 9, 2026BCA memo: about 5% staff cutNotices in December at the earliest

The first time Boeing reached 47 (2017 to 2020)

In the previous cycle, 47 was a waypoint. Supply Chain Dive reported on June 14, 2018 that Boeing would ramp from 47 to 52 a month that week, after Spirit AeroSystems "restored prompt delivery" of fuselages. Boeing had sent a "cavalry" of engineers to Spirit's Wichita plant in April 2018 to get there. The fuselage supplier gated the rate break then, and it would do so again.

By the time of the March 2019 grounding, Boeing "was producing 52 737s a month on its way to a target of 57," according to Reuters. After the grounding Boeing kept building 42 a month, which, Popular Science reported, created a backlog of more than 400 finished airplanes before production was halted in January 2020. The same report pointed to the cost to suppliers that were "asked to dam up their own production lines."

For a supplier, that cycle showed how fast a rate signal can flip. In less than a year, a program that had been heading for 57 went to building aircraft it couldn't deliver, and then to a full stop.

Slip 1: the 2023 plans

In August 2023, Boeing was aiming for 38 a month, and then-CFO Brian West cited a goal of 50 monthly 737 deliveries by 2025-2026, Manufacturing Dive reported. The same quarter, a Spirit quality escape on 737 fuselage sections delayed deliveries, and Boeing sent resources to help with repairs.

That October, Reuters reported that the formal target was still 50 a month for 2025 and 2026, but that internally Boeing planned for at least 57 a month by July 2025. Sources described the schedule as "an important signal to the supply chain that allows smaller companies to make necessary investments." That's the part suppliers should keep in mind. The internal number was the one meant to drive their capex.

Slip 2: the December 2023 master schedule

In December 2023, Reuters reported the 737 master schedule, "which sets the production pace for suppliers." It called for 42 a month in February 2024, 47.2 in August 2024, 52.5 by February 2025 and 57.7 in October 2025 (as cited in Reuters via The Jakarta Post). Rate 42 eventually arrived in October 2025, about 20 months behind that schedule. Every later step has slipped further.

Slip 3: the FAA freeze, January 2024

After the 737 MAX 9 door-plug blowout, the FAA said on Jan. 24, 2024 that Boeing could not expand 737 MAX production. "We will not agree to any request from Boeing for an expansion in production," Administrator Mike Whitaker said, adding that "the quality assurance issues we have seen are unacceptable" (Reuters via The Jakarta Post).

The supply base absorbed the hit within months. By May 2024, Spirit was completing 737 fuselages at about 31 a month, and a Spirit memo said about 400 Wichita employees would be terminated, Forecast International reported. Spirit management blamed its debt load and Boeing's slower production rate. Later in 2024, Boeing announced it would cut about 17,000 jobs, roughly 10% of its global workforce, according to AVweb.

Slip 4: 42 a month, October 2025

On Oct. 17, 2025, the FAA allowed Boeing to raise 737 MAX output to 42 a month from 38, calling it a "small production rate increase" (AP via Spectrum News 13).

On the Oct. 29, 2025 earnings call, Ortberg set the rules for what came next. Increases beyond 42 "will go in increments of five," and "rate increase breaks won't be earlier than six months apart," according to the call transcript. Ortberg also said inventory was doing a lot of the work: "we've got a significant inventory right now, and that's clearly boosting us from going from 38 to 42." At about 47, Ortberg said, Boeing would "start to get more ... aligned with the supply chain in terms of inventory balances."

CFO Jay Malave said on the same call that "Spirit continues to deliver fuselages with improved quality and flow" and that Boeing had "completed the rework on the last of these airplanes and shut down the shadow factory in the third quarter." Boeing closed its acquisition of Spirit AeroSystems on Dec. 8, 2025, according to its third-quarter 2026 10-Q. From then on, the fuselage supplier was part of Boeing.

Slip 5: "this summer," mid-2026

In a June 5, 2026 company feature, Boeing said the three Renton lines were moving "from building 42 airplanes per month to 47 per month this summer." Ortberg hedged: "We'll move when the production system says we're ready to move." Ortberg also said the 737 MAX "supply chain ... is stable to support future rates."

Boeing's second-quarter release on July 28 said "the 737 program began transitioning production to 47 per month rate in the quarter" and had "activated low-rate initial production on the 737 North Line in July." The North Line is in Everett, Leeham News noted, which added a fourth line outside Renton.

Slip 6: wings set the pace, September and October 2026

By the Morgan Stanley Laguna conference on Sept. 16, the summer goal was gone. "We're not stable yet," Ortberg said, and "the area where we're constrained right now is our wings production," Leeham News reported. Ortberg said Boeing still had "pretty high levels of inventory," and Malave said "we certainly have excess inventory of certain commodities." Leeham, citing Cirium, put August 737 deliveries at 41 jets.

On the Oct. 27 call, the delay was made official. "It is taking us longer than we had expected to demonstrate performance at rate 47," Ortberg said. "I am expecting it will take us into next year to get fully stable at this rate" (transcript). Reuters reported that as rate 47 in early 2027. Boeing had previously expected to stabilize at 47 before the end of 2026, Leeham reported.

The constraint hasn't changed. "Wings remain the pacing item on the 737 program," Ortberg said, per Leeham, and "we're not yet to where I can say we're stably producing wings to support the 47-a-month rate." On the next step: "our financial plan will target rate 52 in the back half of 2027," and "it is more important that we do this ramp right than in what particular month we achieve a rate break."

The delivery math followed. Boeing delivered 367 737s in the first nine months of 2026, according to Leeham, and Malave said 737 deliveries would "come in shy of the 500 delivery target" for the year. Getting to 500 would have taken 133 deliveries in the fourth quarter, or roughly 44 a month.

The financials show what the slower ramp costs. BCA posted $10.7 billion in third-quarter revenue and a (6.5)% operating margin. Boeing attributed the margin "primarily" to a less favorable delivery mix, "higher projected costs associated with future production rate adjustments and higher estimated supply chain costs," per its earnings release. BCA delivered 161 airplanes in the quarter, and the backlog stood at more than 6,300 airplanes worth a record $612 billion. Demand isn't the problem. The 787 is "stable at a production rate of 8 per month." The 737 isn't the only line with a parts problem: Malave said "our 777 freighter and 767 tanker production lines were disrupted by a supplier of wing components."

Boeing's free-cash-flow outlook now runs to about $3 billion in 2027, about $6 billion in 2028, and its $10 billion target in 2029.

The inventory problem

The detail suppliers should care about most came in one line on the Oct. 27 call: "we are producing fuselages at a lower rate than the final assembly intentionally to burn down inventory," Ortberg said of Wichita. Boeing now owns Spirit, so the fuselage plant runs below final assembly on purpose. That's the clearest sign that rate gains at Renton won't turn straight into upstream demand.

Wide low view inside a large hall showing several unpainted green fuselage sections lined up on stands beside a parked transporter, with one empty storage bay and a blurred forklift far behind.

The balance sheet backs that up. According to the 10-Q, total Boeing inventories rose to $90.9 billion at Sept. 30, 2026, from $84.7 billion at Dec. 31, 2025, an increase of about $6.3 billion in nine months. Commercial aircraft programs inventory rose to $77.2 billion from $70.8 billion. Deferred production costs on the 737 grew to $14.0 billion from $11.8 billion.

A year ago Ortberg said supplier inventories would come into line around 47. In September he moved that point out: "Once we get to [monthly rate] 52 and 57, that's when you're going to see the supply chain more aligned with us relative to inventories." With 52 now targeted for the second half of 2027, suppliers of commodities Boeing holds in excess should not expect pull to match final-assembly rate until well into 2027, and possibly later.

The Nov. 9 memo

BCA had 50,494 employees as of December 2025, Reuters reported. Outlets estimate a 5% cut at roughly 2,500 jobs. Boeing hasn't given a number. Notices go out in December at the earliest. Reuters noted that many states require 60 days' notice, which puts the first involuntary separations no earlier than February 2027.

A dim planning room with a long table holding a rolled chart weighted by a wrench and a hard hat, beside glowing monitors with abstract content and a window onto a dark hangar.

According to IBTimes UK, citing KMUW, a separate Boeing memo excluded employees in Wichita, Kansas, and Tulsa, Oklahoma, from compulsory redundancies. Wichita is the former Spirit fuselage operation that Boeing is currently running below final-assembly rate.

Pope's reasoning is straightforward. BCA staffed up for a ramp that didn't arrive on schedule, and the gap now shows up as headcount it can't use. It's the same pattern Spirit followed in May 2024, and the same lesson the 2019 grounding taught: hiring for an OEM's planned rate is a bet on the OEM's schedule.

What operators should take from this

Treat the master schedule as a ceiling. Reuters described Boeing's schedule as a signal meant to let smaller companies make investments. Since 2023 that signal has been early by roughly two and a half years at each rate break. Size capacity, hiring and buffer stock to the customer's demonstrated rate, and treat the published schedule as the upside case.

Expect the OEM to burn its own stock first. Boeing said inventory carried it from 38 to 42, and it's now deliberately running fuselages below final assembly. When a customer carries excess inventory of what you make, its rate increases reach you late and in smaller increments.

Watch the pacing item. Wings have set the 737 rate all through 2026, and a wing-component supplier disrupted the 777F and 767 lines. A customer's real rate is set by its slowest stable process, and that's usually visible in call commentary months before any date officially moves.

Gate your investments the way Boeing gates its rate. Ortberg's steps of five, at least six months apart, give suppliers a usable rhythm. Releasing capex or hiring in tranches tied to the customer showing stable output at each step costs less than funding the next rate ahead of time and then carrying idle capacity or cutting staff.

Sources

Share

Frequently asked questions

When will Boeing reach a stable 737 MAX production rate of 47?

On the Oct. 27, 2026 earnings call, CEO Kelly Ortberg said it would take Boeing "into next year to get fully stable at this rate." Reuters reported this as rate 47 in early 2027. Boeing had earlier aimed to make the move in summer 2026.

What is holding back the 737 MAX rate increase?

Wing production. Ortberg said "wings remain the pacing item on the 737 program" and that Boeing was not yet stably producing wings to support 47 a month.

How many jobs is Boeing Commercial Airplanes cutting?

BCA CEO Stephanie Pope's Nov. 9, 2026 memo said the unit will cut about 5% of its workforce through attrition and involuntary layoffs. BCA had 50,494 employees as of December 2025. Outlets estimate about 2,500 jobs, but Boeing hasn't given a number.

When is Boeing targeting 52 737s a month?

Ortberg said Boeing's financial plan targets rate 52 in the back half of 2027. A December 2023 master schedule reported by Reuters had called for 52.5 a month by February 2025.

Why aren't 737 suppliers seeing higher orders yet?

Boeing holds high inventory and is intentionally building fuselages below the final-assembly rate to burn it down. Ortberg said the supply chain would be more aligned on inventories once Boeing reaches 52 and 57 a month.